DCDB Upgrades
The purpose of the DCDB surveys is to upgrade the accuracy of
the existing Digital Cadastral DataBase (DCDB) onto the Map Grid
of Australia (MGA94) Survey Datum.
This involves entering land parcel information by numerical entry
methods into a software package and establishing on-ground accurate
points to control the data set in a least squares adjustment.
METHOD OF SURVEY
Stage 1 - Data Input
The existing DCDB information and digital plan information
(.TIF format) was provided to DSS by City Council.
Plan information was entered for each lot, starting with the
newest plans first. This was to ensure the most recent (and hopefully
most accurate) dimensions were entered for each line segment.
Dimensions were entered into the Spatial Adjustment Engine software
against each registered plan number in order to provide easier
error checking and statistics against each plan.
The simple and user friendly data input box is resembled by the
box on the following page.

The bearing and distance information was entered for each line
and, in this example, we can see that the values entered agree
with both the current DCDB data (in the yellow highlighted area)
and with the previously entered line data from another plan (in
red half way down). This provides an on-screen check of the data
and improves the least squares adjustment strength at adjustment
time by having redundant measurements.
At the time each line is entered, and once all the plan information
has been entered, the user can check if there are any large discrepancies
between the entered dimensions and the DCDB dimension. This is
a good tool for finding gross errors.
The information box for a typical plan is represented as:
We can see for this plan that the digitised points are not exact
when we look at the DiffBear column against the DPBrng column.
This shows that, for this rectangular block, the existing digitised
coordinates are slightly in error. However, when we compare the
length of each boundary (DiffDist), we find that the data entered
is very accurate, and more correct than the original DCDB data.
Jumping a few steps ahead, once the adjustment is completed,
we can now check the adjusted coordinates against the input coordinates
for this same plan. Comparing against the box shown above, the
following box shows us that after the final adjustment, the bearings
of each line are now within about 30 minutes of the estimated
accuracy of a rectangle (that is the DiffBear for each line against
the average Rotation of the plan). Also, the DiffDist for each
line is well within the required 0.1 metres of accuracy.

A statistical tool within the SAE allows us to query the whole
database at the end of the adjustment and determine where any
errors may lie.
Stage 2 - Survey Control
DSS utilise the GPS technology in various modes of operation;
static, kinematic and real-time differential techniques. On this
project, real-time and static methods were used for installation
of survey control.
The real-time method of surveying involves setting a GPS receiver
over a known survey station and emitting a positional correction
via VHF radio link. This correction is received by all roving
receivers and after a few minutes initialisation, the remote receiver‘s
location is computed to an accuracy of better than 0.05 metres,
based on the control station used.
The real-time method of GPS requires correctional data to be
emitted via VHF radio from a known base station with accurate
coordinates. A roving receiver is placed at the new station to
be surveyed for a period of a few seconds up to a few minutes,
until an accurate position is computed.
The roving receiver is moved, usually by vehicle, to the next
station to be surveyed and the process is repeated.
During the days observations, numerous checks to existing control
stations are made and verified in real-time to ensure data integrity.
The static method of observations requires numerous GPS units
to log data for a common time period between stations. This time
is usually 15 minutes plus 1 minute per kilometre of baseline
length, but is almost always longer in time.
Post-processing of the GPS data is required and numerous checks
are made within each network to ensure data integrity. In this
case the data was processed and analysed using Waypoint Consulting’s
“GRAFNET” software.
Checking, Adjustment and Final Data Delivery
By linking accurate ground control points to boundary points in
the DCDB layer, a least squares adjustment can be performed. In
an ideal adjustment, control points on the extremity of the area
would be held fixed and an even spread of control points would
be present throughout the data set.
For a minimal, first adjustment, key ground control points (ie
permanent markers) are connected and an adjustment is run. By
comparing the misclosures to other ground control points (iron
pins and pegs) we can determine if the adjustment in that area
is correct and accurate, or if there is an error in a portion
of the dataset.
Once each area is proved to be correct, the remaining ground
points are held fixed for a final adjustment, thus providing the
most accurate representation of the DCDB. Riparian boundaries
are adjusted by holding all final data fixed as control. This
provides a ‘best fit’ solution based on the original
digitised data for these boundaries. After the final adjustment
is accepted by the Surveyor, the original data set (DCDB) is upgraded
by writing adjusted coordinates for each point in the original
data set.
There are commonly a few graphical errors in each data set of
the DCDB. These could be any of the following:
Extra points
These points are located along a boundary line, usually representing
easement pegs or line pegs, and need not be there for this project.
Incorrect Topology
These are parcel topology inconsistencies as compared to the registered
plan lots. Also, where a corner has been amended, the DCDB may
not have been updated to represent the correct information as
stated on the plan.
Incorrect Parcel Naming
Where a parcel has the wrong “lot_plan” identifier
attached.
In each of the these cases, some user editing is required in
order to provide a clean and accurate data set. Information noted
at the data entry stage process, on standard quality check forms,
enables the data set to be modified after a final adjustment has
been computed, using DSS In-house software PolyEdit Version 1.0.
Using MapInfo Version 7.8, there are three more quality checks
that are run to ensure data integrity.
The first of these is a self-intersection test which identifies
if any line in a parcel crosses itself. This is simply represented
by the following diagram.

The problem most likely occurs when the Surveyor is editing the
data, deleting points and adding new points. This is simply fixed
by swapping the order of the points in the polygon.
The second quality check is to check for any overlaps in polygon
data. Again, this is easily resolved by adding or removing points
in one of the affected parcels.
The third quality check is to check for any gaps between polygons.
Again, this is resolved by adding or removing points in certain
polygons.
The output of a final data set is now produced.
DSS provides final data in MapInfo format, containing both the
DCDB and SCDB layers.
Recent DCDB upgrades include:
Rockhampton City Council view
images
|